Expansion Projects for the Year 2020

Amidst the current pandemic, Metro Kalibo Water District (MKWD) continues to expand its service area, as of December 31, 2020, here are the expansion projects that Metro Kalibo Water District (MKWD) has completed and implemented.

  • Installation of 75mmØ x 500 LM Distribution Line
    • Completed on September 03, 2020, and located at Mahabang Bantod-Int., Pook, Kalibo, Aklan.
  • Installation of 75mmØ x 565 LM Distribution Line
    • Completed on December 22, 2020, and located at Limpawan-Puis, New Washington, Aklan.
  • Installation of 75mmØ x 325 LM Distribution Line
    • Completed on November 03, 2020, and located at Bacan, Banga, Aklan.
  • Installation of 75mmØ x 1,114 LM Distribution Line
    • Completed on November 27, 2020, and located at Taba-ao, Banga, Aklan.
  • Installation of 75mmØ x 200 LM Distribution Line
    • Completed on November 12, 2020, and located at New Buswang, Kalibo, Aklan.
  • Installation of 250mmØ Altitude and Pressure Sustaining Valve (Ochando Steel Tank)
    • Completed on December 02, 2020, and located at Ochando, New Washington, Aklan.